What this page is. An example for the firm answering an RFP, not the agency writing one. The RFP is real and public, from the County of San Mateo, issued September 12, 2017. It is closed. We use it because it shows clearly what a Bay Area public owner asks for. The response outline is ours. We are not lawyers; read each RFP and contract yourself.
The example RFP
The County of San Mateo Project Development Unit issued a Request for Proposals for architectural and engineering services for its New County Office Building at the County Government Center in Redwood City (County of San Mateo RFP, PDF, 47 pages, checked 2026-10-07).
What a small firm should notice first:
- It was a second round. Only firms already pre-qualified and shortlisted through an earlier request for statements of qualifications could respond.
- About five weeks. Issued September 12, 2017. Questions by email by September 18. A mandatory pre-proposal conference on September 20. Answers posted September 22. Responses due October 16 at 2:30 pm. Interviews October 25 and 26. Board approval of the contract November 7.
- Interviews, then negotiation. The county would interview at least three firms, then negotiate with the most qualified first and move down the list if needed.
- Hard format rules. Portrait, 8.5 x 11, bound. No more than 30 single-sided pages, not counting covers, tabs, resumes, financial and bonding information and marketing material, “but will preferably be much shorter”. Type at least 10 point. Firm name and contact details at the top of page one. Cover letter optional. One signed original, 10 copies and one electronic copy.
- No brochures. “Responses that are comprised of standard marketing materials that do not specifically address the items below will not be evaluated.”
- Firm offers. Proposals stayed valid for 90 days after the close.
- Public record. The RFP warned that responses may be disclosed under the California Public Records Act.
What the RFP asked for, and a response outline
The RFP required five sections “in the same sequence listed”. Here is each one with what it asked and what to put in your response.
6.01 Company information and qualifications
Asked: changes to the firm since the qualifications round (ownership, staff size, pending legal actions), any clarifications to that submittal, and the current and forecast workload of the people proposed.
Your response:
- One short paragraph per change, or “no changes since our SOQ dated [date]”.
- A workload table: each proposed person, their current projects, and hours or percent committed for the next [6 to 12] months.
6.02 Team qualifications and availability
Asked: resumes with similar projects, each person’s role and percent availability, their other current and planned work, who attends each meeting, the projected schedule, the Architect of Record, a budget for the engineers and sub-consultants you expect to need, a written promise that the team stays for the whole project, and an org chart.
Your response:
- Org chart on one page, names and roles.
- A team table: name, role, percent availability, other projects.
- Resumes (these did not count toward the 30 pages), each with 3 to 5 similar projects.
- The Architect of Record by name and license.
- A one-line assurance signed by a principal that the named team stays assigned.
6.03 Project approach
Asked: design philosophy for this project, the method including work with the construction manager/general contractor, the number of meetings in each phase with who attends and what each meeting decides, each person’s duties by phase, an overall schedule with review time, phasing so the government center keeps running, structural and MEP approach, Zero Net Energy and LEED, how you would help set a guaranteed maximum price (GMP) inside budget, and agency approvals.
Your response:
- A phase table: phase, meetings, who attends, decisions made, review time.
- A schedule graphic with every phase and county review period.
- One short section per lettered item, with the RFP’s own letter as the heading, so the reviewer can tick it off.
6.04 Compensation
Asked: the county’s Excel “Architect Fee Matrix”, with a lump sum fee broken out by phase, reimbursable expenses (including an allowance for a presentation model), lump sums by phase for any sub-consultants plus markups, hourly rates for all personnel, any extra fee for BIM, and whether the fee changes under design/build or design assist.
Your response:
- Use the owner’s spreadsheet, not your own layout.
- A fee by phase that ties to your hours by phase. Our guide on architectural fee percentage by phase shows how to build one from budget hours.
- Hourly rates for every role on the team.
- Our architecture fee proposal template has the phase table, rates and reimbursables ready to fill in.
Note that this RFP asked for a fee with the proposal. That is allowed, but California law has agencies select architects on qualifications and then negotiate the fee with the top firm (Government Code 4526 and 4528; the fee proposal template guide quotes both). So some Bay Area RFPs ask for a fee now and some ask for it later. Read the submittal list.
6.05 Contract exceptions
Asked: any exceptions to the county’s draft professional services agreement, as redline language. If you list none, the county assumes you will sign it as is.
Your response:
- Read the agreement before you decide to bid, not on the last day.
- Redlines only for the clauses you cannot accept (for example insurance limits or indemnity; check those with your insurer), or a plain “no exceptions”.
How the county scored responses
The RFP listed six criteria and gave no points or weights:
| Criterion | What it covered | Where your response answers it |
|---|---|---|
| A. Completeness | Every item answered, format rules kept | All sections, in order, inside 30 pages |
| B. Personnel experience | The named people, similar civic and office work on dense urban sites | 6.02 resumes and project lists |
| C. Past performance | Work in San Mateo County, the Bay Area or similar; client references | Project sheets and references |
| D. Technical and management approach | Working with user groups, design approach, GMP inside budget | 6.03 |
| E. Availability | The team’s workload | 6.01 workload table, 6.02 percent availability |
| F. Financial stability | The firm’s finances, from the earlier qualifications round or other sources | SOQ financials |
Two of the six (B and E) depend on who is on the team and how busy they are. A firm that cannot show percent availability quickly loses time on every RFP.
Where the time goes
With about five weeks from release to due date, and a mandatory conference eight days in, the go/no-go decision has to come in the first week. Questions to answer before you commit:
- Are we on the shortlist or otherwise eligible?
- Can we attend the mandatory conference?
- Can we name a team that is truly available, with percent time we can defend?
- Do we have similar projects of this type and size to show?
- Can we accept the draft contract, or with which redlines?
- If a fee is due now, do we have hours by phase from a similar past project to build it from?
Keep this library ready before the next RFP
Most of what this RFP asked for is the same from one public RFP to the next. Keep these current, in one shared folder, so step 3 is a copy job:
- Resumes for every person who could be named, updated each quarter, with a list of projects by type.
- Project sheets for finished work: client, size, delivery method, your role, dates, a reference with current contact details, and two or three photos.
- A workload table, by person, with current projects and hours committed for the coming months. The same table answers 6.01 C, 6.02 and criterion E.
- A meetings-by-phase table you can adjust per project.
- A fee by phase built from real hours on finished projects, and a current hourly rate table.
- Standard contract positions: the clauses you usually redline, with the language you use.
- Firm facts: legal name, license numbers, insurance limits, financial statements if the owner asks for them.
The workload table and the fee by phase both come from the same place: hours recorded by project and phase. If those hours are not tracked, both sections are guesses.
Want help with RFP responses?
We work with small Bay Area architecture firms on one admin bottleneck at a time, and RFP responses are one of them. We map how your firm puts a response together today, show where the time goes, and get one piece working, for example a resume and project sheet library that fills the team section from one place. Sometimes the answer is to keep what you have.
To start, email vaughn.workflowaudit@gmail.com with a line on how your last RFP response came together. Or browse all guides.
Questions and answers
What is an RFP in architecture?
A request for proposals is a document an owner, often a public agency or school district, sends to architecture firms to ask how they would do a specific project, who would do it, and often what it would cost. It lists the sections the response must contain, the format, the due date and how responses are scored. Many public owners first ask for a statement of qualifications (an RFQ or SOQ) and send the RFP only to a shortlist, as San Mateo County did in 2017.
What should an architecture RFP response include?
Exactly the sections the RFP asks for, in its order. In the San Mateo County example: company information and changes since the qualifications round, the team with resumes and percent availability, the project approach, a fee broken out by phase, and any exceptions to the county's contract as redlines. The RFP said responses made of standard marketing material that do not address its items would not be evaluated.
How long should an architecture RFP response be?
Whatever the RFP allows. The San Mateo County RFP set a limit of 30 single-sided pages, not counting covers, tabs, resumes, financial information and marketing material, and said the response should preferably be much shorter. Type had to be at least 10 point.
What is an architect's statement of qualifications?
The firm's credentials, sent so an owner can shortlist firms before asking for a fee. The AIA's standard version is Document B305-2021, Architect's Qualification Statement, a form where an architect enters its professional qualifications and owners review them to help select an architect for a project (AIA Contract Documents help center). Public owners often ask for the same information in their own format, as an RFQ or SOQ, before the RFP.
What is an SF330?
The SF330, Architect-Engineer Qualifications, is the federal form for A/E work. Federal Acquisition Regulation 36.702 says it is used to evaluate firms before awarding a contract for architect-engineer services: Part I covers qualifications for one contract, and Part II covers the firm's general professional qualifications. The San Mateo County RFP on this page set its own format instead, so check which one each RFP asks for.
Is there an architectural RFP template I can reuse?
The outline on this page works as one, because it follows a real RFP section by section. Change the headings to match each new RFP's own list. The part that saves the most time is not the outline but a kept-up library of resumes, project sheets and a fee-by-phase table, listed below.